How to properly install Welded Pipe Making Machine
   Connect the power cord of the Welded Pipe Making Machine to the power supply specified by the machine, and jog the motor to observe the direction of rotation. The direction of the motor should be the same as the direction of the label arrow on the motor, or turn on the power switch after the line is connected.
 
   Detailed installation and commissioning of Welded Pipe Making Machine:
 
1. Handling: The Welded Pipe Making Machine should be handled by a forklift.
 
2. Installation: The machine should be fixed horizontally on a stable foundation and grounded.
 
3. Fill the oil: Open the rear side cover of the chassis and add 56 liters of No. 46 anti-wear hydraulic oil to the fuel tank.
 Welded Pipe Making Machine
4. Power on: Connect the power cord of the Welded Pipe Making Machine to the power supply specified by the machine, and jog the motor to observe the direction of rotation. The direction of the motor should be the same as the direction of the label arrow on the motor, or turn on the power switch after connecting the line. If the machine moves, the motor opening is correct, and if the machine is not moving, you need to reverse any two of the three live wires.
 
5. Pressure adjustment: The pressure of the machine system is 31.5MPa, which is adjusted by the relief valve. Welded Pipe Making Machine adjusts the pressure increase clockwise and decreases the pressure counterclockwise. (The pressure has been adjusted at the factory. If you need to adjust the pressure of the relief valve, it is strictly prohibited to use this equipment over 31.5MPa)