News
Home - News

How to properly install Square Welded Tube Mill production line



Connect the power cable of the Square Welded Tube Mill production line to the power supply specified by the machine, and jog the motor to observe the direction of rotation. The direction of the motor should be the same as the direction of the label arrow on the motor, or turn on the power switch after the line is connected.
 
   Detailed installation and commissioning of Square Welded Tube Mill production line:
 
1. Handling: The Square Welded Tube Mill production line should be handled by a forklift.
 
2. Installation: The machine should be fixed horizontally on a stable foundation and grounded.
 
3. Fill the oil: Open the rear side cover of the chassis and add 56 liters of No. 46 anti-wear hydraulic oil to the fuel tank.
 Square Welded Tube Mill production line
4. Power on: Connect the power cable of the Square Welded Tube Mill production line to the power supply specified by the machine, and jog the motor to observe the direction of rotation. The direction of the motor should be the same as the direction of the label arrow on the motor, or turn on the power after the line is connected. Switch, if the machine moves, the mold opening is increased, the motor is rotated correctly. If the machine is not moving, you need to reverse any two of the three live wires.
 
5. Pressure adjustment: The pressure of the machine system is 31.5MPa, which is adjusted by the relief valve. The Square Welded Tube Mill production line adjusts the pressure increase clockwise and decreases the pressure counterclockwise. (The pressure has been adjusted at the factory. If you need to adjust the pressure of the relief valve, it is strictly prohibited to use this equipment over 31.5MPa)